Opened steel oil tank with a cut hatch, absorbent inside, during decommissioning at a Coventry industrial unit

Case study · Coventry

Steel tank decommissioningCoventry

Three 3,500-litre steel tanks and their pipework drained and decommissioned, and a 2,400-litre plastic tank disconnected and sealed, at industrial units on a Coventry estate.

Coventry · West Midlands3 steel tanks + 1 plastic
3 × 3,500 LSteel tanks
2,400 LPlastic tank sealed
PipeworkDrained and capped
DecommissionedLeft in place

The starting point

Old heating tanks behind the units.

A row of industrial units had been heated by oil-fired warm-air heaters fed from steel tanks behind the buildings.

With the heating no longer needed, the units had three 3,500-litre steel tanks, a separate 2,400-litre plastic tank and runs of pipework still connected. The contractor managing the work asked us to make the whole installation safe.

The scope was decommissioning, not removal: the steel tanks were to be drained with their lines and left in place for the owner to deal with later.

Warm-air heater unit standing in an empty industrial unit
Inside one of the units.

The work

What we did.

01

Drain the steel tanks

Remaining oil and sludge were pumped out of all three steel tanks.

02

Clear the pipework

The lines feeding the warm-air heaters were drained and capped so nothing could run back.

03

Seal the plastic tank

The 2,400-litre plastic tank was disconnected and sealed.

On site

Working around let units.

Each tank sat in a tight space between brick walls, and the units themselves were in use or being prepared for new tenants.

We planned the hose routes and pump position so we did not block shutters or loading areas, and worked through the tanks one at a time.

Leaving the tanks drained and isolated rather than removing them kept the cost down and let the owner decide later whether to cut them out.

Inside an opened steel oil tank during decommissioning
Inside a steel tank during draining.

Project photographs

On site.

Empty industrial unit with a green roller shutter door

The result

No live oil left in the system.

All three steel tanks and their pipework were drained and the plastic tank was sealed, so the units no longer had an active oil installation.

Physical removal of the steel tanks stayed outside this job and can be booked separately.

Project questions

Coventry project questions.

What is the difference between decommissioning and removal?

Decommissioning drains and isolates a tank so it is safe; removal takes it off site. Many sites decommission first and remove later.

Can you drain the pipework as well as the tanks?

Yes. We drain and cap the lines so oil cannot leak or run back from the heaters.

Do you work on units that are being re-let?

Yes. We work around tenants, shutters and loading areas and leave the units free of live oil storage.

Can you remove the tanks later?

Yes. Decommissioned tanks can be cut up and removed at a later date.

Project location

More tank work in West Midlands

  1. Areas We Work
  2. West Midlands
  3. West Midlands

Client typeLight industrial units heated by oil-fired warm-air heaters

Same work forGarages and MOT centres, workshops, trade counters

This project was in Coventry, West Midlands. The West Midlands page covers towns, typical sites and the environmental rules there, and the West Midlands region page shows the wider area.

Planning similar work?

Tell us about your tank.

Send a few photos, the tank size if you know it and the postcode, and we will come back with a method, a fixed price and a date.

Call 24/7 Get a Quote