Case study · Bournemouth
Tank pressure test and inspectionBournemouth
A pressure test and inspection visit to a steel fuel tank with a pump unit and hoses, at a warehouse site in Bournemouth, Dorset.
The starting point
Proving a tank, its pump and its lines are tight.
Looking at a tank tells you a lot, but not everything. A pressure test shows whether the tank or its pipework holds when it is under load.
The brief for this Bournemouth visit called for a pressure test and inspection. The tank is a blue steel unit with a pump and dispensing hose, standing in a covered bay beside pallet racking, with a spill kit station and a fire extinguisher close by. The photos show the narrow gap beside the tank, where hoses and cables run past its supports.
Tight spaces like this are where problems hide: the side nobody can see, the base against the floor, and the pipe runs behind the pump.

The work
What we did.
Visual inspection
The shell, supports, base and the floor around the tank are checked for corrosion, staining and damage.
Pump area check
The hoses, nozzle, fittings and the floor of the pump recess are looked at for drips, staining and wear.
Isolate and test
The section under test is isolated and pressurised, then watched for any loss over a set time.
Record
The readings and what was seen are written up with photos.
What the photos show
Rust at the base, oil in the pump recess.
Two of the photos show why a visual check comes first.
At the base of the tank, where it meets the support frame, the steel is heavily rusted and covered in dust and cobwebs. Corrosion at the base is common on steel tanks, because moisture collects where the steel meets the floor and the frame, and it is hard to see without getting down beside it.
In the pump compartment, dark oil staining and black residue lie across the floor of the recess, around the hoses and the dispensing nozzle. Staining like this is noted in the inspection, because it points to drips or seepage around the pump and its fittings.


The result
Visit completed and recorded.
The pressure test and inspection visit was completed and photographed.
The test readings and findings sit in the inspection record for the site, together with the photos of the base, the pump compartment and the surroundings.
Project questions
Bournemouth project questions.
What is a tank pressure test?
The tank or pipework is isolated, pressurised and monitored. A drop in pressure points to a leak.
When is a pressure test needed?
Before reuse, after repairs, when a leak is suspected or when a site is sold or let.
Can you test underground pipework?
Yes. Pressure testing is the usual way to check lines that cannot be seen.
What does rust at the base of a steel tank mean?
Moisture collects where a tank meets its frame and the floor. The rust is checked for how deep it goes, because corrosion that weakens the steel is a reason to repair or replace the tank.
What is checked around a tank pump?
The hoses, nozzle, fittings and the floor of the recess are checked for drips, staining and wear.
Do you cover Bournemouth and Dorset?
Yes. We inspect and test tanks across Dorset, including Bournemouth.
More tank work in Dorset
Client typeWarehouse site with a steel fuel tank and pump
Same work forWarehouses and distribution depots, fleet yards, factories and workshops
This project was in Bournemouth, Dorset. The Dorset page covers towns, typical sites and the environmental rules there, and the South West England page shows the wider region.
Planning similar work?
Tell us about your tank.
Send a few photos, the tank size if you know it and the postcode, and we will come back with a method, a fixed price and a date.