Fuel Still In The Tank
The old tank still held usable fuel. It had to be uplifted into IBCs, kept on site and returned to the new tank rather than written off as waste.
Removal & Decommissioning
Oil Tank Removal & Cold CuttingUnderground Tank RemovalsTank DecommissioningDecommissioning & Foam FillingPlant & Machinery RemovalWaste Oil DisposalInstall, Clean & Maintain
Commercial Fuel Tank InstallationOil & Fuel Tank CleaningFuel PolishingOil Tank InspectionsUltrasonic Thickness TestingOil Tank RefurbishmentEnvironmental Services View all services →

A commercial site in London needed its ageing 9,200 litre oil tank replaced — and the buried line feeding its pump house renewed at the same time.
Britteco removed the old tank, lifted a new bunded tank into the existing bund by Hiab, and installed a completely new two-inch underground fuel line from the tank to the customer's pump house. Every joint was sleeved and set beneath an inspection chamber, and the finished run was pressure tested before any fuel went back in.
The customer had already excavated the main pipe runs and lifted the pathway, so the team had full access from day one. An initial site inspection found no unexpected works, and RAMS were submitted and agreed with the customer before anything started.
The original tank had reached the end of its service life. The replacement sits in the same bund — cleaned and prepared — with new pipework and alarms around it.


Nothing on this site was difficult on its own. What made it a three-day job was the sequence — fuel, tank, pipework and alarms all had to come apart and go back together in the right order.
The old tank still held usable fuel. It had to be uplifted into IBCs, kept on site and returned to the new tank rather than written off as waste.
A hedgerow sits between the access route and the bund, so the new tank had to be lifted over it by Hiab, with a banksman in attendance throughout the lift.
The new two-inch line had to step down roughly a metre from the tank, pass under the pathway beside the pump house, then rise and enter through the wall.
Every joint on the buried run had to stay reachable for inspection, so a chamber was set over each one before any of it was backfilled.
Everything was sequenced so nothing stayed open longer than it had to be — fuel out, old tank away, new tank in, then pipework, alarms and testing.
Fuel uplifted into IBCs, old tank cut up and taken away for recycling, new tank craned into the prepared bund.
Old pipework cut out and isolated, new two-inch line threaded, sleeved and run under the path into the pump house.
Filler cabinet and alarms fitted, the full run pressure tested, fuel restored and the site reinstated.
The first day cleared the bund and put the new tank in place.
Any fuel left in the old tank was uplifted into IBCs so it could go straight back in once the new tank was commissioned. With the tank empty, it was cut up on site and taken away to be recycled.
The new tank arrived at midday. The existing bund was cleaned and prepared while it was offloaded, then the tank was lifted over the hedgerow by Hiab — a lift that required a banksman under the site's health and safety arrangements.

With the tank set, the second day was all pipework.
The customer's old pipework was cut out and disconnected from the pumping station. Isolation points were locked off and equipment switched off before anything was opened up. The pipework that came out was sent away for recycling in line with Britteco's ISO 9001 processes.
The new two-inch line was then installed: stepped down roughly a metre from the tank, run under the path beside the pumping station, then up and through the wall. Each length was cut to size, threaded and made up with PTFE tape and joint paste on every joint, before being enclosed in a plastic sleeve and painted.

The last day connected everything up — and proved it.
The underground run was completed and connected to the customer's equipment, with inspection hatches added over the joints. The filler cabinet was connected to the bund with two-inch pipework: 1.5 metres to a 90 degree elbow, then a levelled run above the tank to a second elbow feeding into it.
A digital bund alarm and an overfill alarm were fitted inside the filler cabinet, with their wiring fed up the pipework and into the tank. Every length of pipework was then pressure tested for leaks to 0.5 bar before fuel went back in and both alarms were tested.

The part of the job that disappears underground is the part worth photographing. This is what went in — and how it was protected before it was covered over.



The site went from an end-of-life tank on old pipework to a new bunded tank, a fully sleeved and chambered two-inch line, and two alarms proven on handover — inside the three days allowed.
With both alarms proven and every joint checked over, fuel was restored to the locked valves and sand and warning tape were laid along the full length of the run before backfilling. The site was left clean and tidy, and the project paperwork was completed and handed over.
Common questions
It depends on access and the pipework. This London job, with a 9,200-litre tank and a new buried fuel line, took three days on site with two engineers, including removal, lift-in, pipework, testing and handover.
It is pumped out before the tank is moved and, where the fuel is in good condition, transferred into the new tank so it is not wasted.
Yes. When a lorry cannot get close, we plan the lift from the nearest suitable position or move the tank in and out by other means. The method is agreed during the site survey.
Old buried pipework can leak without anyone noticing. Replacing the line while the site is already open avoids a second disruption and means the whole supply, from tank to pump house, is new and tested.
A working, tested system with fill point, alarms and pipework checked, plus project records and photographs for your files.
Britteco replaces commercial oil and fuel tanks across the UK — removal and recycling, bunded tank installation, underground pipework, alarms and pressure testing, all handled as one managed project.