
Two underground tanks66,000 litres decommissioned
Preparing and foam filling two legacy tanks for a commercial M&E contractor, with corroded access points and residual diesel to remove.
A decommissioning choice for two legacy tanks
A commercial mechanical and electrical contractor asked Britteco to assess two underground tanks with capacities of 53,000 and 13,000 litres. Together they contained approximately 3,000 litres of residual diesel and sludge.
The contractor needed a practical decommissioning solution and a clear explanation of the available approaches. Britteco began with a site survey and prepared a site-specific Risk Assessment and Method Statement.
Assessing foam and concrete filling
The survey led to two options: concrete filling or foam filling. The team discussed the practical implications of each with the contractor, who selected foam based on cost, convenience and the possibility of removing the fill in future.
That choice was specific to this project. Foam filling and tank decommissioning should be assessed against the vessel, ground conditions and intended use of the site; a single filling method is not suitable for every tank.
Gaining access and removing residual contents
Corrosion around the access points complicated the preparation. Specialist equipment was needed to gain access, and corroded bolts had to be removed to open the hatch.
The team drained the tanks as far as practicable and used vacuum extraction to remove the remaining diesel and sludge before the foam-filling stage. The works required coordination with other contractors sharing the site.
Preparation and tank access formed a substantial part of the job. The project account records additional breathing equipment for the internal work, with the work controlled through the site-specific arrangements.
Decommissioned in situ
Following preparation, the tanks were filled with foam in situ. The existing project record describes a setting period of approximately 24 hours for the material used on this job; setting times depend on the specific system and conditions.
The completed work provided the contractor with a managed solution for both tanks, combining survey, access preparation, extraction and filling.
A different site, the same need for planning
For a harbour setting with a separate two-stage mobilisation, see the North Sunderland Harbour foam-filling case study. For the broader service scope, visit oil tank decommissioning.
Planning similar work?
Tell Britteco about the tank, its contents and the available access. Photographs and site details help the team understand the scope before discussing the next steps.
View all case studies →
